Monday, June 1, 2015

Day 2

Today was not all that involved.  I had to clean up the 6 locations that I applied fiberglass and epoxy yesterday.  Then turn over the 3 panels and repeat the fiberglass process on the outside of panels #1, #2 and #3.

Cleaning up the panels involved removing the bricks and wood blocks, and peeling off the mylar strips from the fiberglassed seams.  It looked really good.  The fiberglass was essentially invisible.  I then cut the extra overlapping fiberglass off of the panels.  I also had to file the edges of the panels with a fine rasp file to remove the excess epoxy.

Next step was to turn the 3 panels over and repeat the fiberglassing process at the 6 seams.  No big deal.


The above picture shows that process complete.

The next several days will be the same process on the remaining panels.  So I'll hold of posting any more information until they are all complete.